Exterior Deck expansion & rebuild of existing upper deck. Construction of a new lower deck at Lakeshore Drive sidewalk level. New custom designed stairs from sidewalk to upper deck, lower "storefront" signage, accent lighting, colored concrete and new logo design in the concrete. 

Project construction started in July 2023, completion In June 202

Progress as of October 2023 

View the TV 6 Broadcast in August 2023

 Project Evening Photos after Completion of Accent Lighting on Signage and exterior stairway from sidewalk to lower and upper decks and the main interior taproom - June 2024

Colorful, Creative, Custom Design New KBC logo (Northern Lights Architecture), stained on both upper and lower decks.

Concept Rendering March 2023

Bar Grating, Slip Resistant Stair Tread, - Heavy Duty Galvanized  Steel Exterior Stairs, from Lakeshore Drive Walkway to Upper Exterior Deck and Rear Entry to Brewery Taproom

Completed Project in June 2024

Spectacular Views from the new 5 foot by 12 foot upper deck bump-out  of the Portage Waterway and glorious sunsets over the Houghton-Hancock Lift Bridge

Keweenaw Brewing Company Website

October 2022

October 2023

March of 2023 - Prior to Start of Construction

Read about the Mining Gazette Announcement of the KBC City of Houghton Planning Commission Approval in March 2023

Cross section drawing of new upper deck 5 feet X 10 feet deck extension, new lower deck 14 feet X 36 feet cantilever  (4 feet), along with custom exterior stairway from lower Lakeside street level to upper deck and existing tap room

Finish Pour on lower deck in October 2023

Solid golden yellow concrete pour in August 2023 on upper deck rebuild & 

5' feet by 12' feet extension

Sealed golden yellow concrete with sawcut diamond control joint pattern on upper deck - September 2023